The project manager then issues a change request. What should the change request authorize?
A. Additional resources using the contingency fund
B. Escalation approval to use contingency funding
C. Team overtime to meet schedule
D. Corrective action based on causes
D. Corrective action based on causes
The Answer is D. Corrective action based on cause
Agreed with Krishna option and explanation
Thanks for the invitation.
Project manager does not have to issue a change request to use contingency funds or call team meeting to speed up the schedule, because a PM is authorized through project charter to do both on his own.
In the given situation he just has to take ( D ) Corrective action based on causes.
Option-D Corrective action based on causes,,,,,,,,,,,,,,,,,,,,