What is a project charter?

 A- lists the names and roles of all project team members.

 B- is most often reviewed when documenting lessons learned.

 C- formally authorizes the existence of a project.

 D- is used to document change requests.

user-image
تم إضافة السؤال من قبل Nader Ali , Technical office manager , AlSafwa Contracting
تاريخ النشر: 2016/09/22
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

I Think Option C is the closer to the Question

مستخدم محذوف‎
من قبل مستخدم محذوف‎

A project becomes a project when it has been formally agreed to. In that process of agreement, theirs must be discussions on exactly what the project entails, and what is to be the objective of the project. 

This formal agreement by the project sponsor and the project manager must then be translated into a document that clearly states the objective of the project. It may also identify the major stakeholders, including preferred vendors and service providers involved. 

The document tyen be used as a basis for scoping the project, which should be presented to the sponsor for approval. 

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

  1. Reporting and Control System

    1. For communication of project activity within and between groups and senior management

    2. Initially for high-cost projects, then for “critical,” then forall projects

  2. Computer Support Systems

    1. Survey with recommendations to determine the amount and cost of computersupport

  3. Procedures Manuals

    1. Document procedures and policies

    2. Preliminary manual available by end of year for operator and usertraining

  4. Project Management Training Course

    1. Provide basic project planning and control skills to personnel directlyinvolved in project management

    2. Follow-on courses to provide software, financial, and contracting skillsneeded by project managers

Ksenija Kancelak
من قبل Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My opinion is that correct answer is c

 

Taha Mustahsan
من قبل Taha Mustahsan , Project Engineer (Distribution) , Sui Northern Gas Pipelines Ltd

i would go for the option c

Waleed Hamdy
من قبل Waleed Hamdy , MEP PROJECTS CONTROL HEAD SECTION , AZMEEL CONTRACTING COMPANY

C- formally authorizes the existence of a project.. correct choice

Mohamed Aboelmagd PMP CCP
من قبل Mohamed Aboelmagd PMP CCP , Project Manager – Civil , Bonyan Almdayen Construction

c- project charter is the first authorised document in the project (initiation stage)  

Mohammed Noser
من قبل Mohammed Noser , Civil Engineer , aalbwardi.com

CHARLY CHOICE project charter  formally authorizes the existence of a project

Ihab Zaki
من قبل Ihab Zaki , Chief Technology Officer (Cto) , EGID

I think the closest answer is c

Md Fazlur Rahman
من قبل Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

The closed answer is "C" as when a project document i.e. charter is approved, it authorises all stakeholders to move ahead with clear direction 

مستخدم محذوف‎
من قبل مستخدم محذوف‎

According to PMI, a project charter should possess the following characteristics at a minimum: It should include a description of the business need the project will meet. It should include a description of the product resulting from the project. It should be issued by a manager external to the project who can satisfy the needs of the project. In addition to these elements, you will generally find a section describing the key objectives and goals of the project. These objectives and goals are often the key assumptions, constraints, and/or target performance metrics for the initiative. In particular, any assumption or constraint affecting the project's schedule, budget, or quality will be listed.