A. Begin estimating the task necessary to complete the scope of work.
B. Identify the stake holders and make sure their requirements are included in the scope of work.
C. Create an activity list and then begin to assign the task to resources.
D. Identify a team and obtain approval for their participation from their functional managers.
My answer is option (A) -----------
Thanks for your invitation. Option A.
B. Identify the stake holders and make sure their requirements are included in the scope of work.
Begin work immediately and provide a schedule is what is asked for. In order to estimate schedule and start work, we need to first have work breakdown structure (WBS) created for the scope, and then define activities to accomplish the packages in WBS. So to me, the best option is A, i.e., to begin estimating the task necessary to complete the scope of work.
when the scope of work is defined already and you are going to execute then you should know what are your needs first i think option A. Begin estimating the task necessary to complete the scope of work. may be good answer
Thanks for the invite.
In my opinion it should to be option B first followed by option A .
I seem option A- Begin estimating the task necessary to complete the scope of work.