The concept of (the) _ states that changes related to one requirement—scope, time, or cost—will at least influence one other element.3?

A. Three-point estimationB. Triple constraintC. Three wise menD. Three needs theor

user-image
تم إضافة السؤال من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com
تاريخ النشر: 2016/10/11
SHAIKH NISAR MOHAMED  SHARIF
من قبل SHAIKH NISAR MOHAMED SHARIF , Project Head , AL Fattan Contracting & Properties Management

Obviously its B: Triple Constraint

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Option B looks the better one

Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. My answer is option B

Ksenija Kancelak
من قبل Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

The right answer is:

 

B. Triple constraint