Which of the following documents is not used as input for the validate scope process?

A. The project management plan, containing the scope baseline consisting of the project scope statement and its associated WBS and WBS dictionary.B. The validated deliverables, completed and checked for correctness by thePerform quality control process.C. The requirements traceability matrix, linking requirements to their origin and tracing them throughout the project lifecycle.D. The RACI matrix, describing accountabilities in case of product rejection.

user-image
تم إضافة السؤال من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com
تاريخ النشر: 2016/10/11
marwan alharran
من قبل marwan alharran , engineer , oredoo qatar and ministry of communication- jordan

The project management plan, containing the scope baseline consisting of the project

Riad Boughannam
من قبل Riad Boughannam , Civil Engineer , Self Employed

Only the RACI matrix is not an input to validate scope.

Ihab Zaki
من قبل Ihab Zaki , Chief Technology Officer (Cto) , EGID

Answer 4

RACI matrix

Thanks for the invitation

Hany Farahat Mohamed Ahmed
من قبل Hany Farahat Mohamed Ahmed , MEP Project Manager , LEEDS

A. The project management plan, containing the scope baseline consisting of the project scope statement and its associated WBS and WBS dictionary.

Javad Taghavi
من قبل Javad Taghavi , Program Manager, Senior Adviser in Project Management , KCE Co.

Option D: RACI( responsible, Acountable, Consult and Inform) matrix is related to responsiblity assignment matrix RAM 

Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. My answer is D

ghazi Almahadeen
من قبل ghazi Almahadeen , Project Facilitator , Jordan River Foundation

Thanks for the invite ............................d

Sattar Abdulkarim  Mohamed
من قبل Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Thank you for the invitation Option D.  RACI Matrix, describing accountability in case of the product rejection.               

مستخدم محذوف‎
من قبل مستخدم محذوف‎

D my answer .......

 .. Thanks for yours ..

hisham abu dagga
من قبل hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

option D

 

Thanks for invitation