ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

The cost baseline is developed during which process?

A. Perform integrated change controlB. Estimate costsC. Develop scheduleD. Determine budget

user-image
تم إضافة السؤال من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com
تاريخ النشر: 2016/10/12
Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is option D

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In process Determine project Budget   -    Option D

Bass Fakih
من قبل Bass Fakih , IT-BackOffice , New York Presbyterian Hospital

The cost baseline or project budget is developed in the Determine Budget process which is a planning process in project cost management therefore D is the answer

ZULFIQAR ALI
من قبل ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

The cost baseline is developed during budget. My answer is D

المزيد من الأسئلة المماثلة