ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

1-What are the Procedures to pour concrete for raft foundation? 2-How to prepare ITP for the project? 3-How to prepare MOSfor substructure?

user-image
تم إضافة السؤال من قبل Ali Alfadhly , Technical Manager , QASBA ENGINEERING CONSULTANCY
تاريخ النشر: 2016/10/21
shameer meethal
من قبل shameer meethal , Senior Project Engineer , Chalmers Engineering

 Prior to concrete we need to clarify the below items

Reinforcement and shutter including the levels need to verify with the drawing. Make sure all the MEP services are kept in place as per drawing( if any).

Concrete mixer need to verify as per approved design, also concrete slump need to be verify,

All the equipments ( like vibrator, cube mould, thermo metre etc) and man power need be ready.

 

Munaf Dhedhi
من قبل Munaf Dhedhi , Senior Planner , Al Fahjan Contracting

There are various methods to pour Concrete for Raft Foundation. Depending upon the Conditions, for Deep Raft Foundations in Retaining Structures, Concrete Pumps with Transit Mixers and Batching Plant tends to be the best option. As for deep Raft foundations the Fall Height of Concrete becomes Critical it is always best to deploy Concrete Pumps.