ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Who is supposed to prepare inspection requests for completed or ongoing activities in a construction site?

 Is it the Site engineer, section engineer or quality engineer?

user-image
تم إضافة السؤال من قبل Vinith Kumar , Projects Quality Manager , Al Nasr Contracting Co. LLC
تاريخ النشر: 2016/11/12

No there is confusion in all these answers.

Suppose that a single party is involved in the project. The job will be done by the site engineer/ site supervisor. Then the site engineer will request the quality controler to come and inspect his job. For this the site engineer will prepare the inspection request. It is very basic understanding that quality controler will check the job based on the site engineer's request. It is not that quality controler will raise the RFI and check his own request. 

In a project where multi parties are involved the contractor site engineer will raise the IR or WIR or 'RFI' and forward it to his QC for inspection. When his QC found it is ok, 

Then this contractor QC will take this IR to consultant/ client for inspection. So the Inspection request is always/ has to be prepared by site engineers not Quality controler.

A quality controler is always an invitee not an invitor. When multi parties are involved this RFI has a  'via' in quality controler. 

No there is confusion in all these answers.

Suppose that a single party is involved in the project. The job will be done by the site engineer/ site supervisor. Then the site engineer will request the quality controler to come and inspect his job. For this the site engineer will prepare the inspection request. It is very basic understanding that quality controler will check the job based on the site engineer's request. It is not that quality controler will raise the RFI and check his own request. 

In a project where multi parties are involved the contractor site engineer will raise the IR or WIR or 'RFI' and forward it to his QC for inspection. When his QC found it is ok, 

Then this contractor QC will take this IR to consultant/ client for inspection. So the Inspection request is always/ has to be prepared by site engineers not Quality controler.

A quality controler is always an invitee not an invitor. When multi parties are involved this RFI has a  'via' in quality controler. 

Pillappan Karuppaiah
من قبل Pillappan Karuppaiah , Coating Inspector , Bureau Veritas

Construction supervisor has to prepare inspection requests and submit to inspector for inspection

mohamed rabie
من قبل mohamed rabie , site civil engineer , Contraco W.L.L

quality control engineer supposed to prepare inspection requests for completed or ongoing activities in a construction site

Balaji Palraj
من قبل Balaji Palraj , Assistant Manager , Parampujya Solar Energy Pvt Ltd ( Teamlease Services Ltd )

It varies between Projects and sites. If you consider a site, then it is the responsibility of the Project Incharge at the site should request for inspections with relevant authorities. If seperate quality assurance engineer is present means ; Then He shall request for inspections with the authorization of the project Head at that specific site.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟