ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Which factors should you consider when adding a resource to your project team?

 

A. The impact the resource will have on the cost of the system

B. The impact the resource will have on the duration of the system

C. The impact the resource will have on the histogram.

D. Whether the resource is available, and if it will have impact on the cost and duration of the system

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/11/26

D. Whether the resource is available, and if it will have impact on the cost and duration of the system

Hima Ann Varghese
من قبل Hima Ann Varghese , Test Analyst , Allianz Cornhil Insurance Services

Expertise of the resource and option D

Sunil Mathew
من قبل Sunil Mathew , Recruitment Officer , Sharjah Aviation Services

Efficiency, Time management, Accuracy + D

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I thing option D is good answer.

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation and I will go with option D .

mamoun mokhtar
من قبل mamoun mokhtar , general manager , albyan technical foungary

i will have to consider option D. Whether the resource is available, and if it will have impact on the cost and duration of the system , for i need the satisfaction of my team as well

Sattar Abdulkarim  Mohamed
من قبل Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Thank you for your question. Option D - Both need to be considered. Therefore, the relevant answer as : whether the resource is available and if it will have impact on the cost and duration of the system.

Ahmad Mohammed
من قبل Ahmad Mohammed

Answer will be "D." because if the resource is available, Projects require specific expertise at specific moments in the schedule, depending on the milestones being delivered or the given phase of the project and if it will have impact on the cost and duration of the system.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Yes Option D is correct one -------------------------------------------

المزيد من الأسئلة المماثلة