Reserve analysis a technique not used in:

 

A. Estimate Costs

B. Estimating Activity Duration

C. Control Costs

D. Determine Budget

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
تاريخ النشر: 2017/01/13
DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I seem option - C. Control Costs is good answer.

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I beg to differ with you Mr.Muhammad , Reserve Analysis technique is used in Control Cost as well. 

In control cost process Reserve Analysis is used to monitor the status of reserves ; to determine whether the same reserves will do or additional reserves needed .

Thanks for the invitation.  

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

I think option C because

Reserve Analysis: Many cost estimators include reserves, also called contingency allowances, as

costs in many schedule activity cost estimates. Reserve Analysis a technique not used in Control

Costs.

Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is B