ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

The scope of a project can be expected to change if:

 

A. The project manager must provide cost estimates without having a design concept

B. All of the other alternatives apply are possible based upon the situation

C. The project manager is assigned after the project is defined, and the cost and schedule are approved

D. A clear objective is not provided

E. Oversimplification (underestimating) of the nature of the work occurs

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/01/28
DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I seem option B. All of the other alternatives apply are possible based upon the situation is appropriate.

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Thanks for the invitation 

 

Ans. B.