A. None of the other alternatives apply
B. A greater likelihood that something will fall through the cracks
C. Less estimating accuracy
D. Lower status reporting costs
E. Better control of the project
Thank you for your invitation. My answer is option A. None of the other alternatives apply.
Thanks for the invitation. I would like to choose option A as my answer.
Thank you for the invitation
I agree with answer A
My answer is for option (A)
My first choice is option A & thanks for the invitation .
E. Better control of the project
The answer is E which is better control