أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
A. Change the project's objectives
B. Call a meeting of the configuration control board
C. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
D. Change the scope baseline
E. Prepare a variance report
C. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
In my opinion appropriate choice shall be to change the scope baseline after consulting with stakeholders , project ream & customer.
B. Call a meeting of the configuration control board
Thank you for invitation. I seem option B. Call a meeting of the configuration control board is good answer.