You are a project manager working on a software development project. You've developed the risk management plan, identified risks, and determined?

risk responses for the risks. One of the risks you identified occurs, and you implement the response for that risk. Then, another risk occurs as a result of the response you implemented. What type of risk is this called?

A. Residual risk

B. Mitigated risk

C. Secondary risk

D. Trigger risk

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/02/11
Sherif Ahmad Abdullatif Mohammad
من قبل Sherif Ahmad Abdullatif Mohammad , Information Security & Network Engineer , Advanced Operations Technology

The risk that resulted from a response of mitigating another risk is called a Residual Risk, the answer is A.

hisham abu dagga
من قبل hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

 

Option C

Sattar Abdulkarim  Mohamed
من قبل Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Appreciation for the invitation. My answer is Option C- Secondary Risk.

مستخدم محذوف‎
من قبل مستخدم محذوف‎

The answer is C, Secondary risk, is a risk that arises as a direct outcome of implementing a response to a risk. 

يوسف دمدوم
من قبل يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Think you for the invitation

I agree the option C : Secondary risk

حمود عبدالرحمن
من قبل حمود عبدالرحمن , مندوب علمي صيدلاني , افاميا

Yes with many companies and organizations

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I seem option C. Secondary risk is good answer.

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Of course it is C - Secondary Risk .

Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is A

Muhammad Umar Farooq
من قبل Muhammad Umar Farooq , IT Program Leader , Petro Rabigh

By definition a secondary risk is the one that arises as a direct result of implementing a risk response.

The answer is C.

 

To get more information on Project Management, follow the following page: