ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

During project execution, a line manager informs you that he will not have sufficient resources available next month to support you and two others?

projects. The best way to handle this problem would be to:

A. Ask the line manager to make the decision.

B. Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.

C. Prepare a purchase order to outsource the work.

D. Ask your sponsor to meet with the line manager.

E. Ask the line manager to work with senior management to prioritize the work

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/02/11
Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Reaction to given situation depends on the " Enterprise Environmental Factors " of an organization. But most common approach is as mentioned in option B .

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.

hisham abu dagga
من قبل hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

Thank you for the invitation

Option B

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I seem option D. Ask your sponsor to meet with the line manager. is good answer.

Sattar Abdulkarim  Mohamed
من قبل Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

My answer is Option D. Ask your sponsor to meet with the line Manager.

Muhammad Ramzan Muhammad Ramzan Dayo
من قبل Muhammad Ramzan Muhammad Ramzan Dayo , Project Coordinator

I would like to arrange meeting with line manager, after discussion our priority will be reach to achieve targets within available sources if not this situation we will arrange meet with seniors to get their value able input for success.

يوسف دمدوم
من قبل يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

I agree the option : E , Ask the line manager to work with senior management to prioritize the work

 

 

Javad Taghavi
من قبل Javad Taghavi , Program Manager, Senior Adviser in Project Management , KCE Co.

Option D can be correct because:

You are countable to sponsor. if you participate to any meeting independently and you committed to some decisions of meeting that they have had negative impact on your project, sponsor will never accept your reasons for negative impacts.

Because sponsors are reponsible for project funding and he is accountable to Portfolio manager(senior manage) then that manager line have to inform his senior manager hierarchically the senior manager to specify the strategic decision 

Anish Ali
من قبل Anish Ali , Head Projects , LM Energy & Software Pvt Ltd

Option E, line manager must work with program manager (senior management) to provide shared resources until the allocated manpower is not back to work.

 

Not being agree with option D as sponsor meeting with line manager may initiate process of hiring outsourced team which might be a time consuming activity resulting delay in project delivery schedule