A. Determine Budget process
B. None of the other alternatives apply
C. Estimate Costs process
D. Control Costs process
A part of Estimate Costs Process.
Cost management plan: Describes how cost variances will be managed and Part of the overall project plan. Output of Estimate Costs process is: Cost estimates and Cost management plan
Thank you for invitation. I seem option C. Estimate Costs process is good answer.
My answer is for option C. Estimate Costs process
Thank you for the invitation. My answer is C