The VP of sales division approaches you and requests that you change the sales registration screen on the sales website to include phone number is?

required filed. This is considered as

A. Project initiation.

B. Project ongoing operation.

C. Project Execution.

D. project closing

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/02/17
Sattar Abdulkarim  Mohamed
من قبل Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

More convenient choice is option B.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion - B. Project ongoing operation.

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I seem option  B is good answer.

hisham abu dagga
من قبل hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

Thank you for the invitation

Option B

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I suppose this happens in project initiation .

Godwin Etim
من قبل Godwin Etim , Bernard Ojeifo Longe V First Bank of Nigeria Plc

Correct answer is A, project initiation. This would be noted as a change request from the intial project scope, and anything that involves project scope is done at the project initiation stage.

Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is B