A. Both1) rearranging conflicting tasks, and2) showing the outer dependencies of tasks
B. showing the outer dependencies of tasks
C. depicting actual versus planned tasks
D. rearranging conflicting tasks
It is C - depicting actual versus planned tasks .
A Gantt Chart provides a graphical illustration of a schedule that helps to plan, coordinate, and track specific tasks in a project. So it matches with your C option.
Thank you for invitation. I seem C. depicting actual versus planned tasks is good answer.