A. Float
B. c and b
C. Total Float
D. Negative Float
Thank you for the invitation
Option B. A&C
Free float is the amount of time an activity can be delayed without affecting the start time of the succeeding activity.
That is right answer
not
Option B. C&B
Thanks for the invitation. My answer is C
Thank you for invitation. I seem B. c and b is good answer.
The answer is C.
There are 2 concepts need to be clarified. Float and Total Float.
Float is the amount of time that an activity can be delayed from its early start without delaying the successor activity.
Total Float is the amount of time that an activity can be delayed from its early start without delaying the project end date.
To get more information on Project Management, follow the following page:
Appreciation for the invitation. It is option A - Float.
My answer is for option (A)
In my opinion - B. c and b
Based on the given network, what is the sum of floats of activities A, B and C (Floats A+B+C) ?
Of course it is C - Total Float .