The Cost of Poor Quality separated these costs into 3 categories:

  • Prevention Costs: Including quality planning, training, preventive maintenance, housekeeping etc.
  • Appraisal Costs: Including testing, inspection, audits, reviews and surveys, etc.
  • Failure Costs:
    • Internal Failures: Including scrap, rework, expediting, equipment downtime, injuries, etc.
    • External Failures: Including product recalls, returned products, complaint handling, lost sales, etc.