You are estimating the duration of the project plan activities, devising the project schedule, and monitoring and controlling deviations from the schedule. Which of the Project Management Knowledge Areas are you working in?
A. Project Integration Management
B. Project Time Management
C. Project Scope Management
D. Project Quality Management
B. Project Time Management
Thank you. The answer probably option B.
Of course it is B - Project Time Management .
____________________B_____________________________
B. is the correct answer. Project time management
Thank you for the invitation
Option B
Thank you for the invitation. My answer is B