ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Considering alternate suppliers is a form of?

A. Value engineering.

B. Project integration

C. Contract Management

D. Risk Analysis

E. All of the other alternatives apply.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/02/24
Babar Latif
من قبل Babar Latif , Sr. Project Engineer , NAMF Corporation

That would be "Risk Analysis" as part of your Project Risk Management.

Alternate vendors added to the pre-qualified ones would be required only in case the main suppliers fail to meet the PO in any way.

I don't think this would be value engineering since the value engineering mainly focuses cost cutting (without compromising the scope, quality or schedule etc.) and you already have short list various suppliers on the pre-qualified list and place the order on the best Valued supplier.

Hussain  Alshagrawi
من قبل Hussain Alshagrawi , Freelancer Consultant , Freelancer

Although option (c) could be the cloesest answer, I believe that having an alternative supplier will be always part of the Risk Management and supply security. Risk analysis would be therefore, part of the Risk Management.

jasmina malnar
من قبل jasmina malnar , Head of Marketing and Indirect Procurement , Hrvatski telekom

value engineering, but also category strategy and negotiation preparation ;)

Elke Woofter
من قبل Elke Woofter , Project Assistant , American Technical Associates

I also go with Option C - Contract Managment

Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is A

Sattar Abdulkarim  Mohamed
من قبل Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

My Answer Option C- Contract Management.

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. I seem correct answer is option A. Value engineering.

Rodolfo Torres
من قبل Rodolfo Torres , Associate , Filinvest International

D seems to be the answer. By having alternative suppliers already imply that one is already thinking of the risks once the suppliers in contract failed or missed out on the set agreement and there should be something to fall back on to be able to meet this agreement with the customer.

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Option C - Contract Management , obviously  .

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion , the appropriate option is A

المزيد من الأسئلة المماثلة