أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
For HMA, said temperature is too low.. In my opinion paving shall not be continued at this temperature.. precaution is always better than rectification.. However if the work is already done we can check the achieved compaction and In-situ air voids through Asphalt cores, in addition to the cores IRI and oter test shall be performed as answered by Engr, Kareem Al Fayoumy