You've constructed the WBS for your recent project. You've requested that the subproject managers report to you in three weeks with each of their?

individual WBSs constructed. Which statement is not true regarding the subproject managers' WBS?

A. The work package level facilitates resource assignments.

B. The work package level defines the agreed-upon deliverables.

C. The work package level facilitates cost and time estimates.

D. The work package level is the lowest level in the WBS.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/03/03
ZULFIQAR ALI
من قبل ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

Answer is D. The work package level is the lowest level in the WBS. This statment is not true, as it can be lower.

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I think option B. The work package level defines the agreed-upon deliverables is good answer.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion

B. The work package level defines the agreed-upon deliverables.

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

It is option D of course & thanks for the invite.