أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
project schedule network diagram and know that you will use only finish-to-start dependencies. Which of the following diagramming methods does this describe?
A. Network template
B. PDM
C. AON
D. ADM
In my opinion the correct option is D
Explanation:
The arrow diagramming method uses only finish-to-start dependencies.
Its option B i.e. PDM (Precedence Diagram Method) which is used for scheduling activities in a project plan. It’s a method of making project schedule diagram using nodes to represent activities and connect them with arrows.
Thank you for invitation. My answer is option D-The arrow diagramming method.
Thank you for the invitation
Option D
I will go with B - PDM and PDM is also referred as AON.
Thank you for the invitation. Sorry, I don't know about it.
The correct answer is Option D - ADM.
My answer is for option (B) PDM