General man hour norms for major activities of project? Such as excavation, masonry, piping jobs, equipments etc. If available in web site, link Pl.

user-image
تم إضافة السؤال من قبل VELUMANI RAJAGOPAL , AGM/ HOD (Responsible for Technical Office & Projects-Mine) , ICS
تاريخ النشر: 2017/03/14
Gandhi Mohankumar
من قبل Gandhi Mohankumar , Construction Project Manager , Golden Sand Engineering Construction

Excavation by equipment = 130~150 cu.m/hr,

Masonry by Mason - Blockwork = 90~120 nos/day, Plastering work = 12~14 sq.m/day

Gnanasambandam Annamalai
من قبل Gnanasambandam Annamalai , Proposals / Subcontracts Manager , Descon Engineering

Every Company has its standard manhours based on its historical data and based on the efficiency and the conditions its been executed, the standard manhours is approximated to evaluate earned manhours 

Arnold San Jose
من قبل Arnold San Jose , Site Architect , Kimly Construction Private Limited

Securing site works to follow as per the schedule

Securing the quality of works

Securing works to follow the correct procedure as per specifications

Securing works to follow as per the local code