ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

What percentage of activities is optimum for a longest path in a primavera baseline schedule ?

user-image
تم إضافة السؤال من قبل Binil Paul , Sr. Planning Engineer , KEO International Consultants
تاريخ النشر: 2017/03/16
ZULFIQAR ALI
من قبل ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

It depends upon the level of schedule; if it is the very high level schedule then it is difficult to say what percent of activities should be on longest path.  However in my experience mostly between 10-15% of activities should be in longest path.