What is claim digger in primavera?

What is the meaning of Claim Digger in Primavera & How to use the tool?

user-image
تم إضافة السؤال من قبل Mohamed Fazl Abdul Azeez , Senior Planner , Focus Design Partner
تاريخ النشر: 2017/03/23
ZULFIQAR ALI
من قبل ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

With the help of Claim digger, we can compare 2 proejcts in order to see what has been changed. Such as previous update and current updated can be compared to see the difference between both schedules.

Kathy Castle
من قبل Kathy Castle , Project Controls Specialist /Forensic Claim Analyst /Consultant , Freelance

The Claim Digger utility in Primavera P6 Professional allows you to compare the many differing schedule features to help you determine if your project file is unique. You can easily compare your current schedule with a revised version of it.

ROHIT SHARMA
من قبل ROHIT SHARMA , PLANNING MANAGER , TATA CONSULTING ENGINEERS

Claim digger is used to compare the projects, using the same we can find out the changes done in project, like change in relationship, adding / subtracting lags in project activities etc.

Hany Ismael
من قبل Hany Ismael

Claim Digger is one of primavera software built in tools: P6 Claim Digger is very useful tool to find difference between two versions of schedule or Baseline Schedules V.S Revised Schedules using primavera P6 without any additional software required. When you should use Claim Digger, Applications of using This tool : 1- When you receive a new version of the time schedule from the contractor, Then you should use Claim Digger to check what has been changed on the schedule. 2- When you Receive an update of the time schedule, you should check that nothing changed from the baseline original duration, relationships and constrains. 3- Before submitting your schedule to the client after new revision or update, just run fast check to ensure that noting went wrong. How to work with Claim Digger Step by Step : Please check this link which contains step by step procedures with photos: https://planningengineer.net/claim-digger-baseline-schedule-v-s-revised-schedule-comparison-tool/