ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Reserve Analysis involves?

 

A. Adding resource reserves to the activity resource estimates

B. Estimating by multiplying the quantity of work by productivity rate

C. Developing project schedule with contingency reserves as a recognition of the schedule risk

D. Incorporating time buffers into the activity duration estimates

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/03/31
Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. My answer is D

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I think C. Developing project schedule with contingency reserves as a recognition of the schedule risk is good answer.

hisham abu dagga
من قبل hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Thanks for the information

 

Option D

 

يوسف دمدوم
من قبل يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

Iagree the option C. 

C. Developing project schedule with contingency reserves as a recognition of the schedule risk

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I will go with option - C & thanks for the invite.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: D

Explanation:

Reserve Analysis ( Contingency ): Project teams may choose to incorporate an additional time

frame, called time reserve, contingency or buffer, that can be added to the activity duration or

elsewhere in the schedule as recognition of schedule risk.

 

المزيد من الأسئلة المماثلة