أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
A. The project office
B. The project sponsor
C. The project team
D. The project manager
E. Anyone associated with the project
E. Anyone associated with the project
Thanks for the invitation. My answer is E
I think the appropriate option is E
Thank you for the invitation
Iagree the option E
Thank you for the invitation
Thanks for the information
Option C
It should be D. As Project Office, is only true, if organisation has PMO. Project Team forms in planning stage.
Charter contains details on Sponsors.
Charter contains a very high level details on project and with high level of Risk/Issue. lot of items yet to be discover in Planning and Monitoring.
One key object of Charter is to assign a project manager and provide him Authorization to work.
So, best possible answer is D.
I will go with option D - The Project Manager .