A. The early finish date is equal to the late finish date.
B. The critical path supports the imposed end date.
C. The late start date is earlier than the early start date.
D. The project is sinking.
E. When leads are employed in the schedule.
Option-C, The last Start date is earlier than the early Start date- is correct answer
Thank you. My answer is Option C-The late start date is earlier than the early start date.
C. The late start date is earlier than the early start date