ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You are a project manager responsible for the construction of a new office complex. You are taking over for a project manager who recently left the?

 

company. The prior project manager completed the scope statement and scope management plan for this project. In your interviews with some key team members, you conclude which of the following?

A. They understand that the scope statement describes how the high-level deliverables and requirements will be defined and verified.

B. They understand that the scope management plan describes how project scope will be defined and verified and used to control project scope.

C. They understand that the scope management plan is deliverables oriented and includes cost estimates and stakeholder needs and expectations.

D. They understand that the scope statement assesses the stability of the project scope and outlines how scope will be verified and used to control changes.

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/04/07
Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. My answer is B

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

Explanation:

The scope management plan describes how project scope will be defined and verified, how the

scope statement will be developed, how the WBS will be developed, and how project scope will be

controlled

Robert Malak
من قبل Robert Malak , Projects Manager , Ankido Oil Services for General Contracts DMCC

Thank you for the invitation, I believe the answer is B.

hisham abu dagga
من قبل hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

Thank you for the invitation

Thanks for the information 

 

I Agree Option B

Gourab Mitra
من قبل Gourab Mitra , Manager IT Project Program and Delivery Management(Full Time Contract/Consulting Role) , IXTEL(ixtel.com)

C should be the better answer

C. They understand that the scope management plan is deliverables oriented and includes cost estimates and stakeholder needs and expectations.

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I will go with option B & thanks for the invite.

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. I seem option B is a good answer.

المزيد من الأسئلة المماثلة