أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
company. The prior project manager completed the scope statement and scope management plan for this project. In your interviews with some key team members, you conclude which of the following?
A. They understand that the scope statement describes how the high-level deliverables and requirements will be defined and verified.
B. They understand that the scope management plan describes how project scope will be defined and verified and used to control project scope.
C. They understand that the scope management plan is deliverables oriented and includes cost estimates and stakeholder needs and expectations.
D. They understand that the scope statement assesses the stability of the project scope and outlines how scope will be verified and used to control changes.
Thanks for the invitation. My answer is B
Answer: B
Explanation:
The scope management plan describes how project scope will be defined and verified, how the
scope statement will be developed, how the WBS will be developed, and how project scope will be
controlled
Thank you for the invitation, I believe the answer is B.
Thank you for the invitation
Thanks for the information
I Agree Option B
C. They understand that the scope management plan is deliverables oriented and includes cost estimates and stakeholder needs and expectations.
I will go with option B & thanks for the invite.
Thank you. I seem option B is a good answer.