ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Your project was just completed. Because of some unfortunate circumstances, the project was delayed, causing cost overruns at the end of?

 the project.Which of the following statements is true?

A. Your project ended because of starvation because of the cost overruns.

B. You should pay particular attention to archiving the financial records for this project.

C. You should document the circumstances as lessons learned.

D. You should document the circumstances surrounding the project completion during the Scope Verification process.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/04/14
Mohamed Kamal
من قبل Mohamed Kamal , Cost Control Manager , China State Construction Engineering Corporation Ltd. (Egypt)

i think it will be (C)

documenting the circumstances as lessons learned.

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. I also think proper answer is option C. You should document the circumstances as lessons learned.

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I will go with option - C & thanks for the invitation.

Mahmoud Abdel Aziz CMA
من قبل Mahmoud Abdel Aziz CMA , Finance Manager , Pan Gulf Telecommunication Co. - Pan Gulf Holding Co.

D. You should document the circumstances surrounding the project completion during the Scope Verification process.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Yes - C. You should document the circumstances as lessons learned.

المزيد من الأسئلة المماثلة