A. Must be completed before all other paths.
B. All of the other alternatives apply.
C. Will elongate the project if the activities on this path take longer than anticipated.
D. Has the greatest degree of risk.
E. Has the greatest degree of risk and will elongate the project if the activities on this path take
longer than anticipated
Critical path is the sequential activities from start to the end of a project.
My answer is
C. Will elongate the project if the activities on this path take longer than anticipated.
Option C is the right choice
F. Is the longest continuous path of the project
In my opinion option - C is most appropriate and thanks for the invite.
C. Will elongate the project if the activities on this path take longer than anticipated
Thank you. I seem Option D. Has the greatest degree of risk is good answer.
E. Has the greatest degree of risk and will elongate the project if the activities on this path take
longer than anticipated