ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

If you are project manager, After a change request has been denied, you should?

A. Forget it

B. Record it and save it.

C. None of the other alternatives apply

D. Pass on to the project team.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/04/20
Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Option - B , denied change request/s should be recorded & saved for future reference purpose.

Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

All the rejected change request should be recorded and file/save it.  So the Option B is the correct choice.

المزيد من الأسئلة المماثلة