أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
as
A. Lag
B. Slack
C. Free float.
D. Restricted float.
E. Level float.
free float_____________________________
In my opinion -----------------A. Lag
Logical Relationship that communicate delay between Start /Finish two activity called "Lag"
Eg. Activity A - RCC Slab Concrete and B. De-shuttering the formwork. Activity "B" Can start after curring Period 21days is called Lag likewise applicable In procurement process That Manufacture and Delivery " Lead Time/Duration " will be considered in lag
Option A is the correct answer
B. Slack --------------------------------
Of course it is A - Lag & thanks for the invite.
Agreed with https://people.bayt.com/rajasekar-subramanian/
Thanks for invitation
Agree Answer Option A