ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You are the project manager for BB Tops, a nationwide toy store chain. Your new project involves a creating a prototype display at several stores?

across the country. You are hiring a contractor for portions of the project. The contract stipulates that you'll pay all allowable costs and an8 percent fee over and above the allowable costs at the end of the contract. All of the following describe this type of contract except for which one?

A. Cost-reimbursable contract

B. CPIF

C. CPF

D. CPPC

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/05/05
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

 In my opinion  - B. CPIF

type of contract is known as a cost plus fee (CPF) or a cost plus percentage of cost (CPPC)

contract. A CPIF is a cost plus incentive fee contract that reimburses allowable costs and adds an

incentive for exceeding the performance criteria laid out in the contract.

MICHAIL KOSTOUROS  PMP PMI-RMP
من قبل MICHAIL KOSTOUROS PMP PMI-RMP , Project Manager , SEEC S.A.

In this question the key word is  except, so the wright answer is D. because CPPC means cost plus percentage of cost, in this type of contract the fee is variable because the fee is based on the costs  

Mohammed Awad
من قبل Mohammed Awad , Operations Coordinator - Jordan and Iraq (Consultancy) , Lutheran world federation

I would say C is the right answer being an added cost.

Sattar Abdulkarim  Mohamed
من قبل Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

It is more convenient answer Option C- Cost Plus Incentive Contract.

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. I seem option B-CPIF is a good answer.

Mohd Almaani
من قبل Mohd Almaani , Field Engineer , Turner Construction

in my opinion the answer is  - B. CPIF

Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option D is the correct choice.

المزيد من الأسئلة المماثلة