A. Estimate Activity Resources
B. Sequence Activities
C. Estimate Activity Durations
D. Develop Schedule
D. Develop Schedule -----------------
The Convenient Answer Option D - Develop Schedule.
Leads and lags is a tool and technique when we sequence activities but Adjusting leads and lags is a technique when we develop schedule and we want also to optimize it. So the best answer is D.
Thank you. My opinion is option D.
Option B. Sequence Activities
Thanks for invitation
I Agree answers Option D
In my opinion option D
Lead and Lags: Since the improper use of leads or lags can distort the project
schedule, the leads or lags are adjusted during schedule network analysis to develop a viable
project schedule. Tools and Techniques for Develop Schedule are: Mathematical
analysis,Duration compression,Simulation,Resource -leveling ,Project management
software,Adjusting Leads and Lags and Coding structure
The righ answer is option B
Thank you for the invitation
i agree the answer D