You are a project manager for Fountain of Youth Spring Water bottlers. Your project involves installing a new accounting system, and you're?

performing the risk planning processes. You have identified several problems along with the causes of those problems. Which of the following diagrams will you use to show the problem and its causes and effects?

A. Fishbone diagram

B. Benchmark diagram

C. Decision tree diagram

D. Simulation tree diagram

 

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/05/18
hisham abu dagga
من قبل hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Agreed with Option A

With greetings and appreciation

Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. My answer is A

يوسف دمدوم
من قبل يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

I agree the option A

Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option A is the correct choice.