ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Assuming no safety stock, what is the reorder point (R) given an average daily demand of 78 units and a lead time of 3 days?

user-image
تم إضافة السؤال من قبل Prabin Rai , inventory officer , bijaya motor
تاريخ النشر: 2017/05/22
Nadeem Asghar
من قبل Nadeem Asghar , Supply Chain Consultant/Trainer , Independent Practitioner

I agree to both of above replies and would like to add the following as well from a reply given by Mostafa Abouelsaad to a very similar question earlier:  

Quote:

However you should also consider the following factors before ordering:

 

  • Is there a minimum order quantity for the needed units?
  • Is it a seasonal product?
  • Is your Purchasing budget enough for the needed units?

Unquote

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

By multiplication of figures -------------

Mohammed Awad
من قبل Mohammed Awad , Operations Coordinator - Jordan and Iraq (Consultancy) , Lutheran world federation

You will need to multiply both numbers together to get the final figure.  This is your safety stock.