Your project sponsor has requested a cost estimate for the project. She would like the cost estimate to be as accurate as possible because this?

might be her one and only chance to secure the budget for this project because of recent cuts in special projects. You decide to use

A: expert judgment techniques

B. analogous estimating techniques

C. bottom-up estimating techniques

D. top-down estimating techniques

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/06/03
Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the correct choice.

Aneesh Shandilya
من قبل Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option C - Bottom-up techniques are the most time-consuming and generally the most accurate estimates

Raihanozzaman  Bhuiyan
من قبل Raihanozzaman Bhuiyan , Manager ce engineer , Cordial Holdings Ltd

a good costin And good materals