In project-driven companies, costs are usually billed againest the project based upon?

 

A. The burdened labor rate of the line organization average salary.

B. The burdened labor rate of the company average salary.

C. The burdened labor rate of the average salary of the project team members.

D. The burdened labor rate of the actual employees who performed the work.

E. None of the other alternatives apply

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/06/03

D. The burdened labor rate of the actual employees who performed the work.

Aneesh Shandilya
من قبل Aneesh Shandilya , Manager/ Lead Electrical , Orpic

It seems it should be Option D - based on The burdened labor rate of the actual employees who performed the work.

Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option D is the correct choice.