أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
A. Both1) be completed in reduced overall time than other projects, and2) be in a higher risk
category than other projects.
B. be completed in reduced overall time than other projects.
C. not be compatible with project risk and assessment
A. Both1) be completed in reduced overall time than other projects, and2) be in a higher risk
Option A is the correct answer
Thanks for invitation
Agree answer Option A
The correct answer is A.
A. Both1) be completed in reduced overall time than other projects, and2) be in a higher risk category then other proejcts.
Out of the given option - A appears to be most appropriate & thanks for the invite.