During development of schedule in Primavera P6, what will you prefer to develop the schedule through, the WBS or Coding?

user-image
تم إضافة السؤال من قبل ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
تاريخ النشر: 2017/06/05
ZULFIQAR ALI
من قبل ZULFIQAR ALI , Project Controls Manager , Nakheel Dubai

WBS is more used now a days as compared to activity coditing strucutre.

Ahmed Elassar MCIArb BSc Eng
من قبل Ahmed Elassar MCIArb BSc Eng , Senior Contract Engineer , Capital Projects Dep. of Qatar University

Work breakdown structure is more detailed to organize the scope of works and its needs

Jawahir Zulfiqar
من قبل Jawahir Zulfiqar

I will prefer WBS while development of schedule in P6. Activity coding can be used for organizing the schedule.

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Earlier using P3 it was very difficult to use WBS and if you wanted to make changes it was a disaster. But now in P6 WBS is more easy and flexible. The best way to go in P6 is WBS, in my opinion.

Binil Paul
من قبل Binil Paul , Sr. Planning Engineer , KEO International Consultants

WBS is the easiest to build 

but if you combine it with Activity codes , then your schedule is more powerful in reporting 

hence a combination is the best option