ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

During development of schedule in Primavera P6, what will you prefer to develop the schedule through, the WBS or Coding?

user-image
تم إضافة السؤال من قبل ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
تاريخ النشر: 2017/06/05
ZULFIQAR ALI
من قبل ZULFIQAR ALI , Project Controls Manager , Nakheel Dubai

WBS is more used now a days as compared to activity coditing strucutre.

Ahmed Mohamed Abdel Kader Al-Assar
من قبل Ahmed Mohamed Abdel Kader Al-Assar , Project Control Engineer , QU

Work breakdown structure is more detailed to organize the scope of works and its needs

Jawahir Zulfiqar
من قبل Jawahir Zulfiqar

I will prefer WBS while development of schedule in P6. Activity coding can be used for organizing the schedule.

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Earlier using P3 it was very difficult to use WBS and if you wanted to make changes it was a disaster. But now in P6 WBS is more easy and flexible. The best way to go in P6 is WBS, in my opinion.

Binil Paul
من قبل Binil Paul , Sr. Planning Engineer , KEO International Consultants

WBS is the easiest to build 

but if you combine it with Activity codes , then your schedule is more powerful in reporting 

hence a combination is the best option

المزيد من الأسئلة المماثلة