How you can calculate burn rate from CPI? Is there any formula?

user-image
تم إضافة السؤال من قبل ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
تاريخ النشر: 2017/06/06
RAYSON MENDOZA
من قبل RAYSON MENDOZA , Sales Operations Coordinator; Executive Secretary; Document Controller; Training Facilitator , Unibeton Ready Mix

Burn Rate = 1/CPI

CPI = EV/AC

Burn Rate = 1/CPI = 1/EV/AC = AC/EV

Burn Rate = AC/EV

Source: http://www.projectmanagementlearning.com/what-is-burn-rate.html

Zulfiqar Ali Abro
من قبل Zulfiqar Ali Abro , Lead Planner/ Scheduler , SNC Lavalin, Calgary Alber

Burn rate formual is BR=I/CP1

ZULFIQAR ALI
من قبل ZULFIQAR ALI , Project Controls Manager , Nakheel Dubai

Burn rate is an indicator used to show how the project is performing with regard to meeting the budget.

Burn rate = 1/CPI

AHMER MUSLIM
من قبل AHMER MUSLIM , Inventory Management , Lucky Motor Corporation Ltd

it is the inverse of CPI (1/CPI)