You are a project manager who has recently held a project team kickoff meeting where all the team members were formally?

introduced to each other. Some of the team members know each other from other projects and have been working with you for the past three weeks during the Planning processes. Which of the following statements is true?

A. Team building begins in the Planning process group. This team is in the forming stage of team development.

B. Team building begins once all the members of the team are identified and introduced to each other. This team is in the storming stage of team development.

C. Team building begins in the Planning process group. This team is in the storming stage of team development.

D. Team building begins once all the members of the team are identified and introduced to each other. This team is in the forming stage of team development.

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/06/11
Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

When all the team members are formally introduced to each other , they are said to be in Forming stage . Hence I will go with option - A and thanks for the invite. 

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. Team building begins in the Planning process group. This team is in the forming stage of team development.

D. Team building begins once all the members of the team are identified and introduced to each other. This team is in the forming stage of team development.