According to the PMBOK Guide, the project manager is identified and assigned during which process?

A. At the conclusion of the Develop Project Charter process

B. Prior to beginning the Develop Project Charter process

C. Prior to beginning the Planning processes

D. Prior to beginning the Preliminary Scope Statement process

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/06/17
andre andre
من قبل andre andre , On Site Sitemanager/Structural /Civil/Mechanical/Tank plate Erection. , Kanye Kanye Projects Africa.

My awnser will be [c] Prior to beginning the planning processes.

sajid kamal
من قبل sajid kamal , Electrical Design Engineer , Jones Nicholsons

Project Manager didnot involve in A B and D, he only involved in option C

Panayotis Dimitrakopoulos,  PMP®
من قبل Panayotis Dimitrakopoulos, PMP® , Project Manager , DEUTSCHE TELECOM GROUP

Th project manager should be selected during Initiating phase of the project since he has to develop the porject charter ,identify the stakeholders etc

hisham abu dagga
من قبل hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Agreed with Option C

With greetings and appreciation

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Prior to beginning the Planning processes

Explanation: According to the PMBOK Guide, the project manager should be identified prior to beginning the Planning processes and is named and authorized in the project charter.