A project is reporting negative cost variance, what is meant by this?

A . Project is under budget B. Project is over budget C. The project is on budget D. None of the above

user-image
تم إضافة السؤال من قبل ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
تاريخ النشر: 2017/06/21
ZULFIQAR ALI
من قبل ZULFIQAR ALI , Project Controls Manager , Nakheel Dubai

The correct answer is B. Project is over budget

Zulfiqar Ali Abro
من قبل Zulfiqar Ali Abro , Planning Manager , Enbridge Inc

Proejct is over budget is the correct answer

MICHAIL KOSTOUROS  PMP PMI-RMP
من قبل MICHAIL KOSTOUROS PMP PMI-RMP , Project Manager , SEEC S.A.

In order to have negative cost variance  , Earn value is less than actual cost so for every $ i earn i spend more so the answer B. Project is over budget, is the correct

Keith Gregory Wright
من قبل Keith Gregory Wright , Program Director , DynCorp International

Each budget item on a project is tracked. When the cost is greater than the budget it is identified as a cost over run or negative cost variance, Item b.

muhammad ahmad
من قبل muhammad ahmad , geologist , oil and gase

SAP makes a distinction between planning and budgeting. Planning implies that an iterative process may occur in which many different versions of the plan may be developed until one is decided upon. The budget which can be defined as a detailed work plan describing how the approved amount will be allocated is developed once the overall plan has been confirmed.

Edmundo Garcia
من قبل Edmundo Garcia , General Manager , HUSSAIN AL BANNAY GERARDO V. PANCHO

PROJECT ENGINEER PROJECT CONCEPT, WHILE SITE ENGINEER IS CONCERNED ON PHYSICAL WORK ON SITE

Ibrahim Noureldin
من قبل Ibrahim Noureldin , Division Financial Manager/Controller , M.C. DEAN

 B. Project is over budget: Cost overrun