You are a Project Manager and takes over a project currently in Execution phase. Where you are going to find best source of information on the?

costs associated with each level of expertise needed for the project:

A. Project Schedule Management Plan

B. Project Staffing Management Plan

C. Project Cost Management Plan

D. Project Quality Management Plan

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/08/11
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

Explanation: Based on the PMBOK, this information would be available in Staffing plan. The Cost management plan would contain cost of scheduled activities.