You are a project manager of ABC Company and your project is currently in execution phase. The customer has requested you for additional work?

This work will affect the budget but not the schedule of the project. What should you do next?

A. Explain the change procedure and ask to submit a request for change.

B. add the additional requirements to the project plan.

C. Discuss with the project team about the change.

D. Ignore the request

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/08/11
hassnain shah
من قبل hassnain shah , Accountant , HRL PVT

FIRST OF ALL I JUST DISCUSS WITH MY TEAM ABOUT THE CHANGE AFTER THE DISCUSS FOR COMPANY I SHOULD GO FOR IT

SYED IRFAN MOHIUDDIN
من قبل SYED IRFAN MOHIUDDIN , Senior Project Manager , AUJAN INDUSTRIAL SOLUTIONS

A . Explain the change procedure and ask to submit a request for change.

ELBOUAZIZI KAMEL
من قبل ELBOUAZIZI KAMEL , Inspecteur De L’éducation Nationale , Inspection de l'enseignement primaire/Circonscription Bardo / Hrayria pour la langue française

Aucun problème. Lui demander de soumettre une demande de changement. Discupter avec lui les tâches supplémentaires. Facturer les ajouts et ajouter une clause dans le contrat concernat les travaux supplémentaires. Discuter avec l'équipe de travail à propos du changement du programme en rémunérant leurs efforts supplémentaires.

asber shaabo
من قبل asber shaabo , ادارة -محاسبة - متابعة شؤون الفندق لدى القطاع العام و الخاص , فندق عينكاوة باﻻص - فندق ارابيﻻ غراند -نقابة محامي كردستان العراق

We will investigate the company's headquarters, labor preparation, internal regulations, market communication, publicity and advertising

Monina Cana
من قبل Monina Cana

execution for pilot study using methodology tools for PI projects.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: A

Explanation: Explain the change procedure and ask to submit a request for change is the best choice.